Construction, Controls, Industrial Rainer Facility Expansion – Garrett Electric

Rainer Facility Expansion

Scope of Work

• A massive new campus for JR Simplot Co featuring three primary components
• A very large Potato Processing Facility (~600k SF)
• A significant, tall High- Bay Freezer (HBF) for Cold Storage (83k SF, 130’ high)
• A substantial Waste Water Treatment Facility (WWTF)
• Requires a massive 40MW of electrical Capacity
• Two new dedicated 13.2kv overhead circuits were installed by Grant County PUD
• Power is distributed underground from the overhead lines to 20 large service transformers
(2500kvs to 4200kva each) located throughout the campus

CATEGORY:

INDUSTRY SERVED:

AREA SERVED: