Scope of Work
• A massive new campus for JR Simplot Co featuring three primary components
• A very large Potato Processing Facility (~600k SF)
• A significant, tall High- Bay Freezer (HBF) for Cold Storage (83k SF, 130’ high)
• A substantial Waste Water Treatment Facility (WWTF)
• Requires a massive 40MW of electrical Capacity
• Two new dedicated 13.2kv overhead circuits were installed by Grant County PUD
• Power is distributed underground from the overhead lines to 20 large service transformers
(2500kvs to 4200kva each) located throughout the campus
- Client: Rainer
- Location: Moses Lake, WA
CATEGORY:
- Heavy Industrial Electrical Construction
- Hydro Maintenance
INDUSTRY SERVED:
- Construction, Controls, Industrial